Beginning the week of June 22nd, the Township will begin our 2026 Road Construction Projects. We appreciate your co-operation during these improvements.
The Roads to be paved are:
Alicia Court – from Charles Blvd. to cul-de-sac
Garfield Ave. – from W. Wyomissing Blvd. to Grand Ave.
Halsey Ave. – from Hillvale Ave. to McKinley Ave.
Reading Ave. – from W. Wyomissing Blvd. to Grand Ave.
Noble Street – from Cecil Ave. to N. Morwood Ave.
Highland Street – from Cecil Ave. to Woodside Ave.
Standford Ave. – from Lawrence Ave. to cul-de-sac
Rosewood Court – from Evergreen to cul-de-sac
Colt Street – from Sage Drive to Conestoga Drive
Conestoga Drive – from Colt Street to dead end
Kay Court – from Gring Drive to cul-de-sac
Kutz Court – from Lindale Drive to cul-de-sac
Update June 18:
Kay Court, Rosewood Court and Kutz Court – work will begin on June 24th through June 26th. There will be “No Parking” signs during working hours.
Highland Street and Noble Street – work will begin July 1st through July 7th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.
Reading Avenue and Garfield Avenue – work will begin July 8th through July 16th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.
Halsey Avenue and Stanford Avenue – work will begin July 22nd through July 28th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.
Colt Street, Conestoga Drive, Alicia Court – work will begin July 29th through July 31st. There will be “No Parking” signs during working hours.
Update June 25:
Kay Court, Rosewood Court and Kutz Court – work will begin on June 29th through July 1st. There will be No Parking during working hours.
Highland Street – work will begin July 6th through July 7th. There will be No Parking during working hours.
Noble Street – work will begin July 6th through July 8th. There will be No Parking during working hours.
Reading Avenue and Garfield Avenue – work will begin July 7th through July 15th. There will be No Parking during work hours. Parking will be allowed over the weekend.
Halsey Avenue and Standford Avenue – work will begin July 16th through July 22nd. There will be No Parking during working hours. Parking will be allowed over the weekend.
Colt Street, Conestoga Drive, Alicia Court – work will begin July 23rd through July 25th. There will be No Parking during working hours.