Update: 2026 Spring Township Paving Projects

Date Published: April 30, 2026

Beginning the week of June 22nd, the Township will begin our 2026 Road Construction Projects. We appreciate your co-operation during these improvements.

The Roads to be paved are:

Alicia Court – from Charles Blvd. to cul-de-sac

Garfield Ave. – from W. Wyomissing Blvd. to Grand Ave.

Halsey Ave. – from Hillvale Ave. to McKinley Ave.

Reading Ave. – from W. Wyomissing Blvd. to Grand Ave.

Noble Street – from Cecil Ave. to N. Morwood Ave.

Highland Street – from Cecil Ave. to Woodside Ave.

Standford Ave. – from Lawrence Ave. to cul-de-sac

Rosewood Court – from Evergreen to cul-de-sac

Colt Street – from Sage Drive to Conestoga Drive

Conestoga Drive – from Colt Street to dead end

Kay Court – from Gring Drive to cul-de-sac

Kutz Court – from Lindale Drive to cul-de-sac

Update June 18:

Kay Court, Rosewood Court and Kutz Court – work will begin on June 24th through June 26th. There will be “No Parking” signs during working hours.

Highland Street and Noble Street – work will begin July 1st through July 7th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.

Reading Avenue and Garfield Avenue – work will begin July 8th through July 16th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.

Halsey Avenue and Stanford Avenue – work will begin July 22nd through July 28th. There will be “No Parking” signs during working hours. Parking will be allowed over the weekend.

Colt Street, Conestoga Drive, Alicia Court – work will begin July 29th through July 31st. There will be “No Parking” signs during working hours.

Update June 25:

Kay Court, Rosewood Court and Kutz Court – work will begin on June 29th through July 1st. There will be No Parking during working hours.

Highland Street – work will begin July 6th through July 7th. There will be No Parking during working hours.

Noble Street – work will begin July 6th through July 8th. There will be No Parking during working hours.

Reading Avenue and Garfield Avenue – work will begin July 7th through July 15th. There will be No Parking during work hours. Parking will be allowed over the weekend.

Halsey Avenue and Standford Avenue – work will begin July 16th through July 22nd. There will be No Parking during working hours. Parking will be allowed over the weekend.

Colt Street, Conestoga Drive, Alicia Court – work will begin July 23rd through July 25th. There will be No Parking during working hours.